Drilling and Abandonment Preparation of CO2 storage wells – Experience from the Ketzin pilot site

Urheber*innen
/persons/resource/prevedel

Prevedel,  Bernhard
WB Scientific Drilling, Scientific Infrastructure and Plattforms, GFZ Publication Database, Deutsches GeoForschungsZentrum;

/persons/resource/martens

Martens,  S.
CGS Centre for Geological Storage, Geoengineering Centres, GFZ Publication Database, Deutsches GeoForschungsZentrum;

/persons/resource/norden

Norden,  Ben
4.1 Reservoir Technologies, 4.0 Chemistry and Material Cycles, Departments, GFZ Publication Database, Deutsches GeoForschungsZentrum;

/persons/resource/janhen

Henninges,  J.
4.1 Reservoir Technologies, 4.0 Chemistry and Material Cycles, Departments, GFZ Publication Database, Deutsches GeoForschungsZentrum;

Freifeld,  Barry M.
External Organizations;

Externe Ressourcen
Es sind keine externen Ressourcen hinterlegt
Volltexte (frei zugänglich)

838918.pdf
(Verlagsversion), 5MB

Ergänzendes Material (frei zugänglich)
Es sind keine frei zugänglichen Ergänzenden Materialien verfügbar
Zitation

Prevedel, B., Martens, S., Norden, B., Henninges, J., Freifeld, B. M. (2014): Drilling and Abandonment Preparation of CO2 storage wells – Experience from the Ketzin pilot site. - Energy Procedia, 63, 6067-6078.
https://doi.org/10.1016/j.egypro.2014.11.639


Zitierlink: https://gfzpublic.gfz-potsdam.de/pubman/item/item_838918
Zusammenfassung
At Ketzin, located west of Berlin, the GFZ German Centre for Geosciences is operating Europe's largest CO2 research storage site. This pilot site has been developed since 2004 and is comprised of one combined injection/observation well and four monitoring wells. From June 2008 to August 2013, a total of 67 kilotons of CO2 were safely injected into the sandstone units of the Upper Triassic Stuttgart Formation in a depth between 630 to 650 m. The paper discusses the well designs and lessons learned in drilling engineering and operations. The abandonment phase started in Ketzin with the first plug cementation of the observation well Ktzi 202 shortly after shut-in of CO2 injection. The experience with the first CO2 well killing operation will be reviewed.